GEBZE-İZMİT TCDD
RAILWAY CONSTRUCTION PROJECT

Relocation of the TCDD Railway Section between Km: 65+830 – 67+244 to a Variant Alignment on the D-100 State Road Gebze–Izmit Section.

Construction

Gebze-İzmit TCDD Railway Construction Project
Construction Methodology

As part of the realignment of the TCDD railway line, the project included 250,000 m³ of earthworks, 35,000 m³ of structural concrete for engineering structures, the installation of prestressed precast sleepers, and the execution of electromechanical systems.


Client: General Directorate of Highways 17th Regional Directorate

Location: Izmit, Türkiye

Construction Period: 2009-2010